Daily Current Affairs for UPSC
Impact of Rising Nuclear Power Costs on India’s Clean Energy Transition
Syllabus- Economy [GS Paper-3]

Context
The cost of four reactors being built at the Kudankulam Nuclear Power Plant (KKNP) has jumped by almost 55% since the Russia-Ukraine conflict, a development that has led to worries regarding electricity tariffs, competitiveness of nuclear power and India’s clean energy goals.
Key Highlights
- Nuclear energy plays an important role in India’s energy transition strategy to make the country energy secure, low carbon and Net Zero by 2070.
- Ongoing nuclear projects, however, are facing a significant challenge due to the increased construction costs, especially for the Kudankulam Nuclear Power Plant (KKNP).
- The projected costs could impact the viability of electricity prices, investment decisions and the speed of the transition to clean energy in India.
- The project cost of Kudankulam Nuclear Power Plant (Units 3-6) has also gone from ₹89,470 crore to ₹1,38,330 crore, a rise of almost 55%.
- The main cause of cost increases was the Russia-Ukraine conflict, which has impacted global supply chains, equipment and logistics costs.
- Other ongoing nuclear projects such as:
- Kaiga (Karnataka)
- Gorakhpur (Haryana)
- Rajasthan Atomic Power Project (Rawatbhata) have also witnessed significant cost revisions.
About Kudankulam Nuclear Power Plant (KKNP)
- Tirunelveli district, Tamil Nadu is the location.
- Developed in collaboration with Russia.
- It is based on VVER (Water-Water Energetic Reactor) technology, which is a variety of Pressurised Water Reactor (PWR).
- Planned capacity:
- Six reactors.
- The reactors are 1,000 MW in size.
- Status:
- Units 1 and 2 are in operation.
- Units 3 & 4 are anticipated to be switched on by 2027.
- Units 5 and 6 will be finished by 2030.
Why Have Project Costs Increased?
-
Global Factors
- The Russia-Ukraine conflict had an impact on the global supply chain.
- Rise in prices of imported nuclear equipment.
- Increased freight and insurance costs.
- Inflation in construction materials.
- Exchange rate changes for purchased parts.
-
Domestic Factors
- Long construction periods.
- Funding and interest expenses.
- Delay in procurement and project implementation.
- Changes in safety standards following worldwide nuclear accidents.
Why Do Rising Nuclear Costs Matter?
-
Higher Capital Costs
- The big investment needed in nuclear plants is upfront.
- The percentage of capital expenditure in the Levelised Cost of Electricity (LCOE) is nearly 60% of the total LCOE.
- This lengthens the construction time and will raise financing costs.
-
Impact on Electricity Tariffs
- If there is a cost overrun, this can be expressed as:
- Higher electricity prices.
- Increased burden on power distribution companies.
- Lower consumption prices for consumers.
- If there is a cost overrun, this can be expressed as:
-
Competitiveness
- Expensive nuclear projects could be less competitive than:
- Solar power.
- Wind energy.
- Hybrid renewable systems.
- Expensive nuclear projects could be less competitive than:
-
Investor Confidence
- An increased cost of the project has the potential to impact:
- Private sector participation.
- Foreign investment.
- Technology partnerships.
- An increased cost of the project has the potential to impact:
Importance of Nuclear Energy for India
-
Energy Security
- Reduces reliance on fossil fuels.
- Delivers stable, base-load electricity.
-
Climate Commitments
- Generates minimal amount of greenhouse gas emissions.
- Helps achieve India’s “Net Zero by 2070” goal.
- Helps achieve the target of increasing non-fossil fuel-based electricity capacity.
-
Stable Electricity Supply
- Nuclear energy is unlike other energy sources such as solar and wind power, which only generate electricity when conditions are favorable.
-
Industrial Development
- Encourages indigenous use of nuclear technology.
- Enhances high tech manufacturing & scientific research.
Challenges Facing India’s Nuclear Programme
- Rising construction costs.
- Long implementation times for projects.
- High financing costs.
- Concern of the public about nuclear safety.
- Nuclear waste management.
- Acquisition of land and environmental clearances.
- Reliance on imported technology and components for reactors.
Government Initiatives
- Opening up the civil nuclear industry for private companies to participate.
- Encouraging collaboration with:
- Russia.
- France.
- United States.
- Promoting indigenous 700 MW Pressurised Heavy Water Reactors (PHWRs).
- Growth of domestic production of nuclear power plants.
Way Forward
- Improve indigenous reactor technology, minimize dependence on imports.
- Improve project management to minimise construction delays.
- Encourage the production of nuclear components in the country.
- Spread international technology partnerships.Spread international technology partnerships.
- Keep track of project expenses and ensure on-time project completion.
- Implement a combination of nuclear and renewables in the energy mix.
- Improve the financing system to lower interest rates for long-term projects.
Source: The Indian Express
Mains PYQ
Q. With growing energy needs should India keep on expanding its nuclear energy programme? Discuss the facts and fears associated with nuclear energy. (2018)